Request performance, payment, or bid bonds in Washington

WA public-works contracts over $35K require performance + payment bonds under the Little Miller Act.

Start with the project, the requested bond, and your deadline. Market eligibility, underwriting, and available capacity must be reviewed before a bond can be offered.

Or call (509) 866-6294

Performance and payment bonds are how owners and subs get protected on construction

Construction is one of the few industries where the buyer (the project owner) pays substantial money before receiving the finished product. The risk that the contractor takes the money and walks away β€” or completes the work with such poor quality that the project becomes unusable β€” is real and historically common enough that statutory and contractual protections grew up around it. Performance bonds and payment bonds are the financial mechanism that makes large construction projects possible by transferring the contractor-default risk from the owner and subs to a third-party surety.

Washington's Little Miller Act (RCW 39.08) requires both performance and payment bonds at 100% of contract value on most state and local public-works projects over $35,000. The performance bond protects the project owner: if the contractor defaults, the surety either funds project completion (typically by hiring a replacement contractor) or pays the owner the cost difference up to the bond face value. The payment bond protects subcontractors, suppliers, and laborers: if the prime contractor fails to pay them, they file claims against the payment bond and the surety pays them out, then pursues the prime contractor for repayment.

Private commercial projects vary widely. Some private GCs and owners require both bonds on every contract, some require only performance, some accept letters of credit or self-funded retainage instead. The trend is toward more bonding requirements as project sizes grow and as more sophisticated owners insist on the protection. The strategic implication for contractors: building a strong surety credit relationship over time is one of the highest-leverage moves a growing contractor can make. Bonded contractors face less competition on bid day because under-capitalized competitors cannot match the bond capacity.


Six bond types WA contractors carry

Performance Bond

Guarantees contract completion per terms. If contractor defaults, surety either funds completion or pays owner the cost difference. Typically 100% of contract value face. Required on WA public works.

Payment Bond

Guarantees subcontractor and supplier payment. If prime contractor fails to pay subs, they file claims against the payment bond. Typically 100% of contract value, paired with performance bond on public works.

Bid Bond

Guarantees the contractor will honor the bid if awarded β€” sign the contract and post the performance/payment bonds. If contractor walks after winning, surety pays the owner the bid spread. Typically 5–10% of bid value.

Maintenance Bond

Covers post-completion defects for a specified warranty period (typically 1–2 years on public works). Pays for repair or replacement of contractor-caused defects discovered after final acceptance.

Public Works (Little Miller Act)

WA RCW 39.08 requires performance + payment bonds on most state and local public works contracts over $35K. Federal projects use the federal Miller Act with similar structure but different thresholds.

Private Commercial

Increasingly required by sophisticated GCs and owners on large private projects. Contract-driven rather than statutory. Some accept letters of credit or self-funded retainage as alternatives.


Bond capacity needs review for your project

Start an assisted request with the principal, project owner, bond requirement, and exact deadline. Unknown details are welcome; staff will identify what is needed next. This request does not verify market eligibility or establish approved bond capacity.

Describe the required bond forms or link a public bid packet now. Secure document collection is arranged by staff. There is no document upload here, and you do not need to provide a Social Security number or financial documents to start this request.

Propeller remains an optional external self-service portal. Products and availability are determined in that portal; our link does not verify that a particular contract bond is available. Pricing and timing are not guaranteed.


Request a project-specific bond quote

Premium is quoted for the individual project and contractor. Provide the contract value, deadline, required forms, schedule, financial statements, completed-project history, and current work in progress. Ask for any bid-bond charges as part of the quote.

Approval, pricing, terms, capacity, and issuance timing are subject to underwriting. Approval is not guaranteed. Submitting a request does not issue a bond.

Request performance / payment bonds β†’


What WA contractors should know about the bond environment beyond the basics

Two specific points worth knowing about the WA performance/payment bond environment. First, the Little Miller Act's $35K threshold is for the original contract β€” change orders that push a contract above the threshold do not retroactively trigger a bond requirement, but new contracts above the threshold do. WA agencies are reasonable about this; they typically include the bond requirement in the bid documents from the start when they expect the contract to exceed the threshold. The trap is private commercial work: contracts that creep upward through change orders sometimes blow past the bond capacity the contractor originally established with the surety, leading to mid-project capacity issues. Disclose expected change orders at quote time.

Second, surety credit underwriting in WA is reasonably consistent with national standards. The state does not have unusual regulatory wrinkles that complicate bond issuance. Where WA does add friction is in the WA L&I prevailing-wage compliance for public works β€” bonded contractors must keep prevailing-wage records cleanly, file the required documents on time, and respond to L&I inquiries promptly. A prevailing-wage compliance issue mid-project can trigger a default declaration and bond claim even when the underlying work is on schedule. We flag this on every public-works bond inquiry because the compliance failure mode is real and avoidable with the right back-office practices.



WA performance bond questions we hear most

Performance bonds and payment bonds are issued together on most public-works contracts and protect different parties. The performance bond guarantees the project owner (the obligee) that the contractor will complete the work according to the contract β€” if the contractor defaults, the surety either funds completion or pays the owner the cost difference up to the bond face value. The payment bond guarantees subcontractors, suppliers, and laborers that they will be paid for work and materials supplied to the project β€” if the prime contractor fails to pay them, they file claims against the payment bond. Both bonds typically run for the full contract value and stay in force through final completion plus the warranty period. WA Little Miller Act (RCW 39.08) requires both bonds on most state and local public works contracts over $35K.

On WA public-works contracts subject to the Little Miller Act, both are required by statute β€” there is no option to provide only one. RCW 39.08 mandates a payment bond at 100% of contract value plus a performance bond at 100% of contract value. The same surety typically issues both as a paired package, and the contractor pays a single combined premium. On private commercial projects, the contract terms dictate the requirement: some private GCs and owners require both, some require only performance, some require only payment, and some accept letters of credit or self-funded retainage instead of bonds entirely. The honest read on bidding strategy: if you can routinely qualify for surety on both, your competitive set on bid day is materially smaller because most under-capitalized contractors cannot. We help contractors build the surety credit relationship over time so the bonded contracts become accessible.

Voluntary bonding on private commercial work is unusual but occasionally strategic. The cases where it makes sense: a contractor with limited project history wants the surety's implicit endorsement to win a competitive bid against more-established competitors, an owner is sophisticated enough to value the bonded protection but did not require it in the bid documents, or a project is large enough that the owner's lender requires bonding even though the contract did not. The cases where it does not make sense: small-dollar private residential work where the bond premium materially compresses margin, projects with short timelines where the bond underwriting cycle does not fit the project schedule, and projects where the GC has explicitly priced the bid assuming no bonded contractor. Most contractors should not voluntarily bond unless there is a specific strategic reason. We talk through the math on every voluntary-bond inquiry.

Surety underwriting considers capital, capacity, and character as well as credit. Underwriters may review working capital, completed-project history, work in progress, prior claims, references, and financial statements. Approval and single-project or aggregate capacity depend on surety review; neither a credit score nor an existing relationship guarantees approval.

Send the request with the exact deadline, time, and time zone, even if other details are unknown. Staff must review market eligibility, project requirements, and underwriting before confirming what is possible. An existing surety relationship does not establish availability for a new project. Pricing, issuance, and timing are not guaranteed. Describe the required bond form or share a public bid-packet URL now; staff can arrange secure document collection if more information is needed.

Start your contract bond request

Share what you know about the project and deadline. Your request remains pending review; it is not a quote, approval, carrier submission, or issued bond.

Check My RateCall